When does a contract become unconditional in QLD? It happens when every condition in the contract has been satisfied or waived, usually once you have given the seller notice on the finance and building and pest conditions by their dates.[1] From that moment you can no longer end the contract under those conditions, and you are committed to settle.

This guide is about that moment: what “unconditional” means, how the condition dates lead to it, how to ask for more time, and what happens if a date is missed. It follows the standard REIQ/QLS residential contract. For the earlier five-day window, see our guide to the cooling-off period in QLD, and for the rest of the document, our guide to the contract of sale in QLD.

Key takeaways

  • A contract is unconditional once every condition has been satisfied or waived.
  • For each condition you must give the seller written notice by 5pm on its date.
  • If you have not given notice by then, the seller may end the contract.
  • You have no right to extend a condition date on your own; the seller must agree.
  • An auction contract is usually unconditional from the fall of the hammer.

What “unconditional” means

A conditional contract is binding, but gives you a way out if a condition is not met. In the standard contract the main conditions are finance (approval of your loan on terms satisfactory to you) and building and pest (written reports on terms satisfactory to you).[1] Other conditions can be added as special conditions, such as the sale of your current home, and they only protect you if they are written into the contract when you sign.[2]

Once all of those conditions are dealt with, there is no condition left to rely on, and the contract is unconditional. From then on you must settle on the settlement date. Our guide to the settlement process in QLD explains what happens next.

Unconditional is not the same as the end of the cooling-off period. The statutory cooling-off period runs for 5 business days from the day you receive the contract signed by both parties, and lets you end the contract for any reason, at a cost of up to 0.25% of the price.[3] A contract can come out of cooling-off and still be conditional for weeks.

How a contract goes unconditional

Each condition in the standard contract works the same way. You must take reasonable steps to satisfy it, then give the seller notice that it has been satisfied or waived, or that it has not been and you are ending the contract.[1] Notices under the contract must be in writing.[1] The contract goes unconditional when the last of those notices says “satisfied” or “waived”.

  1. Building and pest. You get the reports, read them, and if you are satisfied, your solicitor gives notice by 5pm on the inspection date. Our guide to building and pest inspections in Queensland covers what to look for.
  2. Finance. Your lender gives formal approval, you check the terms, and your solicitor gives notice by 5pm on the finance date.
  3. Any special conditions. Each is dealt with as its own wording says.
  4. Confirmation. Ask your solicitor to confirm in writing that the contract is unconditional, and from what date.

Only give a “satisfied” notice when you are. Formal loan approval is not the same as pre-approval, and a building report with items you have not yet priced is not a report you are satisfied with.

An example timeline

Say a contract is dated Monday 2 November 2026 with an inspection date of Monday 9 November and a finance date of Monday 16 November. The cooling-off period ends at 5pm on Friday 6 November.[3] Notice on building and pest is due by 5pm on 9 November, and on finance by 5pm on 16 November.[1] If both notices say “satisfied”, the contract is unconditional on 16 November, or earlier if both are given sooner.

If a finance or inspection date falls on a day that is not a business day, it moves to the next business day, and under the standard contract 27 to 31 December are not business days.[1] Your contract’s dates are whatever was negotiated; read them from the reference schedule.